OUR SERVICE STANDARDS

 

A.     ISSUANCE OF LOCATIONAL CLEARANCE AND CERTIFICATE OF ZONING COMPLIANCE FOR APPROVAL OF BUILDING CONSTRUCTION

Requirements          :           Lot Title or Tax Declaration, Building detailed Cost and Estimates, Application for Zoning Compliance,

Vicinity map or Site Development Plan, Assessment of Fees (may vary depending on the uses and Total Project Cost)

 

Fees                          :           For  Single residential structure attached or detached ,the project cost of which:

1. P100,000.00 and below                                          P288.00

2. Over P100,000.00 to P200,000                               P576.00

3. Over P200,000.00                                                   P720.00 +1/10 of 1% in excess of P200.00

 

For Apartments/Townhouses

1. P500.00 and below                                                 P1,440.00

2. Over P500,000.00 to P2,000,000.00                                P2,160.00

3. Over P2,000,000.00                                                P3,600.00 + 1/10 of 1% in excess of P2,000,000.00

regardless of number of floors

                                             For Dormitories

              1. P2,000,000.00 and below                                              P3,600.00

                                             2. Over P2,000,000.00                                                P3,600.00 + 1/10 of 1% in excess of P2,000,000.00

regardless of number of floors

 

                                             For Institutional

                                                         1. Below P2,000,000.00                                           P2,880.00

                                             2. Over P2,000,000.00                                                P2,880.00 +1/10 of 1% of cost in excess of

P 2,000,000.00

 

                                             For Commercial, Industrial and Agro-Industrial

                                             1.Below P100,000.00                                                  P1,440.00

                                            2. Over P100,000.00  to P500,000.00                                  P2,160.00

                                             3. Over P500,000.00 to P1,000,000.00                                P2,880.00

                                             4. Over P1,000,000.00 to P2,000,000.00                             P4,320.00

                                             5. Over P2,000,000.00                                                P7,200.00 + 1/10 of 1% of cost in excess of

P2,000,000.00

 

          For Special Use/Special Projects (Gasoline Stations, Cell Sites, Slaughter House,Treatment Plant, and others)

1. Below P2,000,000.00                                              P7,200.00

                                             2. Over P2,000,000.00                                                P7,200.00 + 1/10 of 1% of cost in excess of

P2,000,000.00

 

 

HOW TO DELIVER THE FRONTLINE SERVICE

 

Steps/Procedures

It will

take you

 

 

Please approach

1

Give application form to be filled-up by owner applicant & for notarization.

3 minutes

 

 

ARNOLD J. CABRERA

Project Development Officer I

 

2

Check and verify the completeness of the required supporting documents

3 minutes

3

Computation/Assessment of fees

3 minutes

4

Issuance of Order of Payment

2minutes

5

Issuance of Certificate of Zoning Compliance/Decision on Zoning

 

5 minutes

6

Approval of the Deputized Zoning Administrator

1 minute

ENGR. JOSE O. MAGBANUA

Mun. Planning & Development Coordinator

 

TOTAL PROCESSING TIME

17 minutes

 

 

Hits: 363