Programs and Infrastructure Projects

Category: Municipal Engineer's Office Published: Wednesday, 20 July 2016 Written by Super User

A.     FOR ISSUANCE OF CERTIFICATE OF OCCUPANCY

Requirements       :           Certificate of Completion for Building and Electrical and revised plans (if any)

Fees                       :           As prescribed in the Building Code of the Philippines (PD 1096)

 

 

HOW TO DELIVER THE FRONTLINE SERVICE

 

Steps/Procedures

It Will Take You

Please Approach

1

Receive duly accomplished “Certificate of Completion” for Building and Electrical and revised plan, if there is any.

5 Minutes

ENGR. LEONE ESCANILLA

Engineer I

RODOLFO JONIECA

Administrative Aide III

2

Verify duly accomplished “Certificate of Completion” for Building and Electrical and revised plan, if there is any.

 

20 Minutes

ENGR. LEONE ESCANILLA

Engineer I

3

Assessment of “Certificate of Occupancy “ Fees.

10 Minutes

ENGR. LEONE ESCANILLA

Engineer I

RODOLFO JONIECA

Administrative Aide III

4

Endorsement of “Certificate of Completion” for Building and Electrical to the Bureau of Fire (BFP) for issuance of Fire Safety Inspection Certificate  (FSIC).

15 Minutes

RODOLFO JONIECA

Administrative Aide III

  5

BFP verifies if the building complies with the provisions required in the Fire Code of the Philippines and submit findings to the Office of the Building Official.

Maximum of 5 Working Day

BFP

  6

Personnel from both BFP and the Office of the Building Official conducts inspection of the building/structure.

1 Working Day

BFP

ARCH. NHEALLABIAO  

Architect I

ENGR. BOBBY GALOPO

Engineer II

ENGR. LEONE ESCANILLA

Engineer I

7

The Office of the Building Official receives the Fire Safety Inspection Clearance (FSIC) from BFP.

5 Minutes

RODOLFO JONIECA

Administrative Aide III

8

Preparation of the “Certificate of Occupancy”

15 Minutes

MA. JUNEZEN I. MARZOÑA

Administrative Aide VI

ANN LESLIE JARANDILLO

Administrative Aide III

9

Approval

1 Working Day

ENGR. EDGAR I. TANCHUAN

Municipal Engineer

ARCH. NHEALLABIAO  

Architect I

ENGR. BOBBY GALOPO

Engineer II

ENGR. LEONE ESCANILLA

Engineer I

10

Issuance/Release of “Certificate of Occupancy”

15 Minutes

RODOLFO JONIECA

Administrative Aide III

 

TOTAL PROCESSING TIME

7 days 1 hour & 20 minutes

 

 