Building Permit

Category: Municipal Engineer's Office Published: Wednesday, 20 July 2016 Written by Super User

A.     FOR ISSUANCE OF A BUILDING PERMIT

Requirements       :           Documents stated on the checklist

Fees                       :           As prescribed in the Building Code of the Philippines (PD 1096)

 

 

HOW TO DELIVER THE FRONTLINE SERVICE

 

Steps/Procedures

It Will Take You

Please Approach

1

Receive/verify/evaluate/check Application for Building Permit with Plans and the required documents submitted by the client.

15 Minutes

ENGR. LEONE ESCANILLA

Engineer I

RODOLFO JONIECA

Administrative Aide III

2

Assessment of Building Permit Fees

10 Minutes

3

Endorsement to the Bureau of Fire Protection (BFP) for issuance of the Fire Safety Evaluation Clearance.

15 Minutes

RODOLFO JONIECA

Administrative Aide III

4

BFP evaluates submit findings of the Fire Safety Evaluation Clearance (FSIC) to the Office of the Building Official.

Maximum of 5 Working Days

BFP

  5

Office of the Building Official receives from the BFP the result of the Fire Safety Evaluation Compliance of the Application for Building Permit Plan.

 

 

NOTE: If the Plans does not comply with the requirements of the Fire Code of the Philippines, inform the Client and furnish them with a copy of recommendations from the BFP.

 

5 Minutes

 

 

 

 

1 Working Day

RODOLFO JONIECA

Administrative Aide III

  6

Approval

1 Working Day

ENGR. EDGAR I. TANCHUAN

Municipal Engineer

ENGR. JOSE MAGBANUA

Mun. Planning & Development Coordinator

ARCH. NHEALLABIAO  

Architect I

ENGR. BOBBY GALOPO

Engineer II

ENGR. LEONE ESCANILLA

Engineer I

7

Issuance/Release of Building Permit

15 Minutes

RODOLFO JONIECA

Administrative Aide III

 

TOTAL PROCESSING TIME

7 days 1 hour

 

 

 

CHECKLIST OF BUILDING APPLICATION REQUIREMENTS

o  Building, Sanitary and Electrical permit Applications

o  Certified Copy of Tax Declaration/TCP/Contract of lease;

a)                  In case the applicant is the registered owner of the lot, the following documents are required:

1. Certified True copy of TCT

2. Tax Declaration

3. Current Real Property Tax Receipt

b)                 In case the applicant is not the registered owner of the lot, the following documents are required:

1. Duly notarized copy of the Contact of Lease, or

2. Duly notarized copy of the Deed of Absolute Sale, or

3. Duly notarized copy of the Contract of Sale

o  Current Tax Receipt

 

CHECKLIST(For all  buildings having an area of more than 20 sq.m. - up) FIVE (5) SETS OF PLAN   

 

A. Architectural (Signed and sealed by a Civil Engineer or Architect)

o  Location Plan       

o  Site Development

o  Floor Plan

o  Elevation (at least four)

o  Section (at least two)

B. Structural (Signed and sealed by a Civil Engineer or Architect)

o  Foundation Plan

o  Floor Framing Plan

o  Detail of Footing/Column

o  Roof Framing Plan

o  Detail of Structural Members

o  Wall Footing Detail

o  Structural Design and Analysis

C. Sanitary (Signed and sealed by a Sanitary Engineer or master plumber)

o  Plumbing Lay-out

o  Isometric drawing of sewage and water lines

o  Detail of Septic Vault

o  Plumbing Symbols and Specifications

D. Electrical (Signed and sealed by an Electrical Engineer)

o  Electrical Lay-out Plan

o  Design Analysis/Schedule of Loads

o  Riser Diagram

o  Electrical Symbols and Specifications

 

 

(Additional requirements for more than 2 storey buildings)

o  Earthquake Analysis/Seismic Analysis

o  Boring Test Results

o  Five (5) sets of Specifications duly signed and sealed by a Architect or Civil Engineer

o  Five (5) sets of Bill of Materials and Estimates duly signed and sealed

o  Zoning Clearance

o  Road Right of Way Clearance

o  One (1) machine copy of the Architect or Civil Engineer’s PTR and PRC

 